Wednesday, June 30, 2010
Tuesday, June 29, 2010
Sunday, June 27, 2010
Small dome complete!
Well, inside at least! Jason and Michael put in a long Sunday to finishe the first layer of the small dome, and get the second dome ready for complete rings. Soon we can remove the interior intersection guidework!
Starting to take shape
Michael works on the final courses
Dome done!
Jason and dome both finished at the end of the day!
Great progress on Friday and Saturday
Friday and Saturday saw more great participation from BAC Local 3. Pete put it well when he commented how it was a pleasure to volunteer where your profession is actually needed. We're so grateful to have these skilled craftsmen with us.
Dave J. laying the "herringbone" belt around the base of the small dome
The inside of the large dome begins to define the space
Tim lays tile in the second layer
Father and son team of Tim and Pete make great progress with the tile on the inside of the big dome.
Dave J. laying the "herringbone" belt around the base of the small dome
The inside of the large dome begins to define the space
Tim lays tile in the second layer
Father and son team of Tim and Pete make great progress with the tile on the inside of the big dome.
Thursday, June 24, 2010
Progress
Union Craftwork
Yesterday and today were days of incredible progress. Thanks to the men of BAC Local 3 the domes are well on their way. We even started the 3rd and final layer today, which will be the visible side of the shell. The level of skill and professionalism these men show is amazing, and their dedication to building the bowls is a real testament to them.
The Bowls at the beginning of the day Thursday
Tuesday, June 22, 2010
Masonry on site!
Monday the members of the Brickworkers and Allied Craftworkers Local 3 arrived and began working their masonry magic. Dave, Tom, Dan, Randy and Tim have quickly learned the tile-vaulting techniques and are fast becoming experts in the field of vault building.
Tom (left) and Dan laying the first course of Xella AAC tiles
The state of play at the end of the first day
Tom uses a staple gun to fix the geotextile reinforcing to the dome
Masonry at the end of the day Tuesday
Tom (left) and Dan laying the first course of Xella AAC tiles
The state of play at the end of the first day
Tom uses a staple gun to fix the geotextile reinforcing to the dome
Masonry at the end of the day Tuesday
Sunday, June 20, 2010
Ready for Masonry!
Friday, Saturday and Sunday have been very big days of progress as we get ready for the masonry construction to start on Monday. It's been a few days of hard labor and now some visible forms for the domes
20,000 lbs of masonry mortar for construction, all carried up to the sculpture court by hand.
Pallets of aerated autoclaved concrete tiles ready for dome building
The guidework begins to take shape and define the form of the domes
Sunday at noon, with all the guidework completed
Friday, June 18, 2010
When The Bowls are complete
Thursday, June 17, 2010
The Plinth almost Finished!
Today saw some rapid progress from partially framed plinth in the morning to fully decked plinth by the afternoon. I even got to lay out the dome on the deck to check its size and positioning. All the guidework and prep happens tomorrow and over the weekend, with masons showing up on Monday.
Unistruct steel will support the access stair at the corner
Done!
Wednesday, June 16, 2010
Isolation plinth on site
Xella AAC Arrives at American Steel
Aerated Autoclaved Concrete (AAC or aircrete) arrived today courtesy of Xella USA, the manufacturer. Our semi of material arrived after an all-weekend drive from the plant in Georgia -- some of the AAC was still warm from being made only 2 weeks ago!
Unloading the AAC inside American Steel
6 pallets take up most of our rented space...and weigh about 20,000 lbs
Jewlia cutting the blocks into the tiles we will need for the build.
Unloading the AAC inside American Steel
6 pallets take up most of our rented space...and weigh about 20,000 lbs
Jewlia cutting the blocks into the tiles we will need for the build.
Monday, June 14, 2010
A Big day for Big Steel
Today 9500 lbs of steel arrived on site, all of which had to be carried by hand up to the sculpture court. The heaviest piece is a bit more than 650 lbs, and vather awkward. We managed, thanks to a great crew of volunteers and the team from Matarozzi Pelsinger Builders. By the end of the day 3/4 of the plinth was assembled in place and level.
The first steel arrives onsite at 9 am. The first of two trailers full of ochre goodness.
The team handling the largest piece of steel after getting it up the staircase on the right.
Celebration when the final pieces of steel are on the sculpture court.
Most of the steel laid out and set up on the isolation bases. It rocks! (literally...) Only 6 more sections to put in. A lot of good work for one day. Thank you, everybody!